Jump to content

Kishanganga Hydroelectric Project

Coordinates: 34°38′56″N 74°45′05″E / 34.64901°N 74.75151°E / 34.64901; 74.75151
From Wikipedia, the free encyclopedia

Kishanganga Dam
Kishanganga Hydroelectric Project is located in Jammu and Kashmir
Kishanganga Hydroelectric Project
Location of Kishanganga Dam in Jammu and Kashmir
Kishanganga Hydroelectric Project is located in India
Kishanganga Hydroelectric Project
Kishanganga Hydroelectric Project (India)
Coordinates34°38′56″N 74°45′05″E / 34.64901°N 74.75151°E / 34.64901; 74.75151
StatusOperational
Construction began2007
Opening date19 May 2018
Construction costRs. 5783.17 crore ($864 million USD 2016)[1]
Owner(s)NHPC Limited
Dam and spillways
Type of damConcrete-face rock-fill
ImpoundsKishanganga River
Height37 m (121 ft)
Reservoir
Total capacity18,350,000 m3 (648,000,000 cu ft)
Active capacity7,550,000 m3
Inactive capacity10,800,000 m3
Maximum water depth30.48 m
Normal elevation2,390 m msl
Kishanganga Hydroelectric Plant
Coordinates34°28′21″N 74°38′06″E / 34.47250°N 74.63500°E / 34.47250; 74.63500
Operator(s)NHPC
Commission date19 May 2018
TypePelton
Hydraulic head646 m (2,119 ft)
Turbines3 x 110 MW Pelton-type
Installed capacity330 MW
Annual generation1,713 million kWh[2]

The Kishanganga Hydroelectric Project is a run-of-the-river hydroelectric scheme in Jammu and Kashmir, India. Its dam diverts water from the Kishanganga River to a power plant in the Jhelum River basin. It is located near Dharmahama Village, 5 km (3 mi) north of Bandipore in the Kashmir valley and has an installed capacity of 330 MW.

Construction on the project began in 2007 and was expected to be complete in 2016. It was halted in 2011 due to a dispute with Pakistan under the Indus Water Treaty, which went to a court of arbitration. Pakistan protested the effect of the project on the flow of the Kishanganga River to downstream areas in Pakistan-administered Kashmir. In December 2013, the Court ruled that India could divert water for power generation while ensuring a minimum flow of 9 cumecs (m3/s) downstream to Pakistan.[3][4]

All three units of 110 MW each were commissioned and synchronized with the electricity grid by 30 March 2018.[5] On 19 May 2018, Indian Prime Minister Narendra Modi inaugurated the project.[6]

Design

[edit]
Kishanganga Hydroelectric Project is located in Kashmir
N–J project
N–J project
N–J project
N–J project
Kishenganga project
Kishenganga project
Kishenganga project
Kishenganga project
Location of the Neelum–Jhelum and Kishanganga projects in Kashmir

The Kishanganga (Neelum) River is a major tributary of the west-flowing Jhelum River. Located to its north, the Kishanganga flows at a higher elevation than the Jhelum. Both the rivers originate in Indian-administered Kashmir and flow west into Pakistan-administered Kashmir, joining near Muzaffarabad. This situation presents a unique opportunity of diverting waters from the Kishenganga river into the Jhelum river through a tunnel and using the consequent flows to generate power. Both India and Pakistan have explored the possibility and came up with the Kishenganga project and the Neelum–Jhelum project respectively.[7]

Project plan

The Kishanganga project includes a 37 m (121 ft) tall concrete-face rock-fill dam which diverts a portion (58.4 m3/sec) of the Kishanganga River south through a 23.20 km (14.4 mi)[8] tunnel. The tunnel is received by a surge chamber before sending water to the underground power house which contains 3 x 110 MW Pelton turbine-generators. After the power plant, water is discharged through a tail race channel into Bonar Nallah, another tributary of Jhelum (at 34°28′23″N 74°38′06″E / 34.473°N 74.635°E / 34.473; 74.635). After a short distance the Bonar Nallah drains into the Wular Lake, on the course of the Jhelum River. The drop in elevation from the dam to the power station provides a hydraulic head of 646 m (2,119 ft).[9]

The dam is equipped with a lower level orifice spillway to transfer flood water as well as silt downstream to protect the power generation reliability and the operating life of the project.[10] The arbitration award permitted the lower level orifice spillway as envisaged by India but prohibited the depletion of dead storage.

Indus waters dispute

[edit]
Kishenganga project in the context of India and Pakistan

The waters of the Jhelum river and its tributaries are allocated to Pakistan under the Indus Waters Treaty of 1960 (part of the three 'western rivers' – Indus, Jhelum and Chenab). However, India is allowed "non-consumptive" uses of the water such as power generation. Under the treaty, India is obliged to inform Pakistan of its intent to build a project six months prior to construction and take into account any concerns raised by the latter.

Pakistan strenuously objected to the project, claiming that India was not permitted under the Treaty to divert waters from one tributary to another.[11] Experts have disagreed with this contention. John Briscoe, a former World Bank water expert, points out that the "far-sighted Indian and Pakistani engineers" who drafted the treaty very well anticipated the situation.[12] The paragraph 15 of Annexure D states,

Where a Plant is located on a tributary of the Jhelum on which Pakistan has any agricultural use or hydroelectric use, the water released below the plant may be delivered, if necessary, into another tributary but only to the extent that the then existing agricultural use or hydroelectric use by Pakistan on the former tributary would not be adversely affected. (emphasis added)[12]

Nevertheless, Pakistan maintained that the diversion of water was prohibited. Asif H. Kazi, an influential water professional, declared, "the treaty absolutely forbids India from undertaking their project".[13]

Other than the legal objection, Pakistan also had concerns that the project would affect the flow of waters into Pakistan-administered Kashmir along the Kishanganga riverbed, impacting agriculture in "thousands of acres" as well as Pakistan's own planned Neelum–Jhelum project downstream.[11] Experts estimated that the impact on the Neelum–Jhelum project would be only about 10 percent,[14] because 70 percent of the waters of Kishanganga/Neelum are generated within Pakistan-administered Kashmir (after passing through the Kishanganga project)[15] and the project itself reduces the flow by only 21 to 27 percent.[14][note 1]

Unable to agree with India, Pakistan raised a 'dispute' under the Indus Waters Treaty, asking the World Bank to assemble a Court of Arbitration. This was the first time a Court of Arbitration (CoA) was assembled under the treaty.

Court of Arbitration

[edit]
Judge Stephen Schwbel, chairman of the Court of Arbitration

A Court of Arbitration assembled under the Indus Water Treaty is expected to have seven members, two members each nominated by India and Pakistan, and three 'umpires' appointed by recognised authorities: the chairman appointed by the United Nations secretary-general and the World Bank president, a legal member/umpire appointed by US Chief Justice and Lord Chief Justice of England, an engineer member/umpire appointed by the President of MIT and the Rector of Imperial College, London.[17] A distinguished panel was thus assembled to hear the case.[18][note 2]

The Court began by rejecting Pakistan's arguments that the Kishanganga project violated the provisions of the treaty.[18] Then it considered whether the project satisfied the treaty's requirements for hydroelectric plants. Article III(2) obligates India to "let flow all the waters of Western Rivers" and "not permit any interference with the waters".[18] Pakistan argued that the project violated Annexure D of the treaty in three respects:[19]

  • by the permanent diversion of waters from one tributary to another,
  • by failure to conform to the requirements for a permitted run-of-the-river plant (by locating the plant along a diversion rather than at the dam site), and
  • by a diversion of waters between two tributaries that was not "necessary".

The court rejected all three objections by analysing the treaty and its negotiating history.[19]

The final question was whether the diversion met the requirement of protecting "the then existing agricultural use or hydro-electric use by Pakistan". The court addressed the issue with a sophisticated Vienna Convention analysis. It rejected Pakistan's "ambulatory" interpretation that all its future uses that might evolve over time were protected, and upheld India's interpretation that only those uses existing when Pakistan was given complete information about the project were protected.[19] The court determined that the Neelum–Jhelum project did not exist at the time the Kishenganga project "crystallized". Hence, it was not protected by the treaty provisions.[20]

The court upheld India's right to proceed with the Kishanganga project. But it also concluded that the treaty and the customary international law required India to ensure a minimum environmental flow along the Kishanganga/Neelum riverbed. After requesting additional data from India and Pakistan to determine the requirements for minimum flow, the court determined this to be 12 cumecs at river crossing point into Pakistan. Balancing this figure against India's right to the satisfactory operation of its project, it set down 9 cumecs as the required minimum flow to be ensured at all times.[21] The remaining 3 cumecs flow is met from the Indian territory downstream of the Kishangana dam. The loss of power generation is estimated as 5.7% of total generation in a year. However, CoA has not deliberated the possibility of reducing the loss by converting the excess dead storage above the gates as storage for proving the minimum environmental flow during the lean flow season.

Drawdown flushing

[edit]
Schematic cross section of the dam and the reservoir

Pakistan also raised another dispute at the same Court of Arbitration, questioning India's plan to use drawdown flushing for clearing the sediments that accumulate below the 'dead storage' level.[note 3]

Sedimentation is a serious problem among Himalayan rivers (since the Himalayas are young mountains).[23] The previous Salal project on the Chenab river was constructed without drawdown flushing facility and the dam is said to have filled up with sediment within two seasons.[17] For the Baglihar Dam, India insisted on the drawdown facility, leading Pakistan to raise a 'difference' under the Indus Water Treaty. It was referred to a neutral expert appointed by the World Bank, who ruled that the drawdown flushing facility was necessary. India depended on the precedent value of this ruling in designing the Kishanganga project.

Pakistan's concern with the drawdown facility is that it provides India with manipulable storage of water.[24] If the water is drawn down then, while it is being refilled, the gates would be closed and starve the downstream areas of water.[25] In the event of a war or conflict, India would have the ability to flood the downstream areas by using the drawdown facility and then shut off water while refilling the reservoir.[26] So Pakistan perceives the drawdown facility as a key security issue.[27] Indeed, the Indus Water Treaty stipulates that the water storage in the reservoir should be maintained above the dead storage level except in emergencies:

The Dead Storage shall not be depleted except in an unforeseen emergency. If so depleted, it will be re-filled in accordance with the conditions of its initial filling.[28]

India argued that the ability to flush sediment was necessary to assure its right to generate hydroelectric power.[20] The Court obtained technical evidence and expert opinion before determining that the drawdown flushing was not an absolute necessity. Other methods of sediment control were available even if they were less economical.[29] The court read the treaty's provisions regarding depletion and the limits on live storage as restricting India's ability to manipulate flows.[20] According to former World Bank water expert John Briscoe, it might be convenient for India to practise sediment flushing, but it had to be balanced against Pakistan's water security. The court implied that the Baglihar neutral expert erred in not balancing the two concerns. It overruled neutral expert's decision for all future projects.[30]

Prolonged issues

[edit]

After the partial award of the Court of Arbitration (CoA) on 18 February 2013, India resumed the construction of the project. CoA in its decision/verdict dated 18 February 2013 unequivocally permitted India to construct the project as proposed by India (except drawdown flushing operation) without any modification after disposing of all the pending issues raised by Pakistan. The CoA decision categorically declared as quoted below (page no 201)[31]


C. This Partial Award imposes no further restrictions on the construction and operation of the Kishenganga Hydro-Electric Plant, which remain subject to the provisions of the Treaty as interpreted in this Partial Award.


The CoA also declared that it is competent enough as per provisions of the Indus Water Treaty to decide on all the technical issues that are in the domain of the NE (paras 483 to 491). Albeit, Neutral Expert (NE) is to be appointed when India or Pakistan asks accordingly irrespective of differences or disputes (technical or legal issues). Per Article IX (2b) of the Treaty, NE shall give decision only on the issues falling in his domain and recommend other issues to be settled by a CoA. Another possibility for a CoA is when both parties agree so which is the case in Kishanganga dispute.

Pakistan approaching CoA or NE again on the Kishenganga project is not permitted as Pakistan can not raise fresh objections as per Annexure D(10) of the Indus Water Treaty. Pakistan has not asked any clarification on the CoA verdicts as permitted.

Even then Pakistan continued to raise other objections via the bilateral Indus Commission for publicity purposes.[32] These were considered 'technical aspects' and India wisely selected the appointment of a NE to resolve them so that Pakistan commits violations of the Treaty. However, Pakistan insisted on assembling a second CoA. India did not agree to the demand cleverly. The World Bank was faced with conflicting demands from the two parties and called for a "pause" in December 2016 asking India and Pakistan to agree on a course of action. There was no further movement afterward till the completion of the Kishenganga project.[27]

According to Feisal Naqvi, former counsel for the Government of Pakistan, Pakistan's concern is that India did not alter the design of the Kishenganga dam in the light of the court's determination. While the court's ruling prohibited drawdown flushing, the low-level orifice outlets that would enable such flushing still remain. A NE decision to declare them "illegal" would have been necessary for Pakistan.[27]

India never agreed that the low-level orifice outlets were purely meant for drawdown flushing. As acknowledged by the CoA (paras 507 to 509), the low-level orifice outlets, as permitted by Annexure D (8d) of the Treaty, are also needed to pass the probable maximum flood, to release water in the event of an unforeseen emergency and for sediment control by sluicing without depleting the dead storage. It is stated in the court's proceedings that they would be useful for sediment control generally, even without drawdown flushing.[33][note 4] An unforeseen emergency situation can be a tsunami wave created by an avalanche or a glacier lake outburst, taking place in the upstream river catchment area of the dam, which may over top the dam with high velocity water if water level in reservoir is not reduced drastically in time. So the sluice gates are to be located at the bottom most feasible level economically when dead storage is more than 75% of total storage of the reservoir in a run of the river project.

Project details

[edit]
Kishenganga River near Habba Khatoon

Construction

[edit]

The survey work for the Kishanganga project was undertaken prior to 1988. In that year, the Pakistan's Indus Commissioner became aware of the survey and asked India to pause work.[3][35] In 1994, India informed Pakistan its plans for a project with a storage capacity of 0.14 MAF.[36][37] After receiving Pakistan's objections, it revised the project from a storage project to a run-of-the-river project.[37]

During the period 2004–2006, the project moved forward, having been taken up by National Hydroelectric Power Corporation (NHPC Limited).[3] The construction of the tunnels was carried out by Hindustan Construction Company jointly with UK-based Halcrow Group. The first 14.75 km of the tunnel was constructed using a tunnel boring machine operated by SELI,[38] and the remaining 8.9 km by the contentional drill and blast method. It is one of the longest headrace tunnels in India with overburden (height of the mountain above the tunnel) of 1470 metres. Using tunnel boring in the young Himalayan mountains and the adverse climate in winters posed considerable challenges to the construction team.[39][40][41][42]

Commissioning

[edit]

Indian Prime Minister Narendra Modi inaugurated the Kishanganga power plant in the state of Jammu and Kashmir on 19 May 2018. The 330MW Kishanganga hydropower station, work on which started in 2009, is one of the projects that India has fast-tracked in the volatile state amid frosty ties between the nuclear-armed countries. "This region can not only become self-sufficient in power but also produce for other regions of the country," Modi said in the state's capital, Srinagar. "Keeping that in mind we have been working on various projects here for the past four years." Pakistan has opposed some of these projects, saying they violate a World Bank-mediated treaty on the sharing of the Indus River and its tributaries upon which 80 percent of its irrigated agriculture depends.

Benefits

[edit]

In addition to generating 330 MW power, the diverted water from the Kishanganga River is used for the purpose of irrigation or to generate additional electricity from the downstream Lower Jhelum (105 MW), Uri (720 MW) and proposed Kohala (1124 MW) (in Pakistan-administered Kashmir) hydel projects located on the Jhelum River.[43][44]

Future development

[edit]

It was stipulated by the CoA that India shall release 9 cumecs subject to adequate inflows in the reservoir for the purpose of minimum environmental flows into the Kishenganga River[45] Though there is no stipulation per IWT to maintain minimum environmental flows for a run of the river hydropower plant and India offered voluntarily to release the minimum environmental flows downstream without contesting the environmental flow requirement. CoA stipulated the same as the requirement under Customary international law.[21] The CoA verdict (page 43) also made provision to contest the minimum environmental flow requirement in future after 7 years from the commissioning of the Kishenganga power plant.[45] As per clause 1 of Annexure D of the treaty, India can use the available water fully for hydropower generation in an unrestricted manner subject to complying with the restrictions imposed in Annexure D. There is no stipulation in Annexure D for sparing water to the downstream for the purpose of minimum environmental flows. As per clause 29 of Annexure G, whenever the relevant treaty stipulations are not extant then only other acceptable international laws such as customary international law are applicable. Thus CoA has provided an option to rectify omissions of India in the future so that the Kishenganga power project becomes economically viable as the stipulated minimum environmental flows are nearly 25% of the total inflows.

In the case of storage works, Annexure E(20) of IWT clearly permits that the stored water can be used fully in any manner by India without the need to release water downstream for minimum environmental flows.[46] The average water yield is 4.1 cumecs (129 million cubic meters per year) in the river catchment area below the Kishanganga dam before the river enters Pakistan as stated in page 171 of the CoA decision dated 18 February 2013.[31] Downstream of the Kishanganga dam, the river is taking a U-turn to enter Pakistan territory. Nearly 20 million cubic meters capacity gross storage dam can be envisaged close to the LoC to impound all the inflows which can be further pumped through a 6 km long tunnel into the upstream Kishenganga dam reservoir. The augmented water into the Kishanganga dam reservoir is also diverted to the Jhelum River to generate additional power by the 330 MW power plant. As the pumping head (90 m) is not exceeding 15% of the 664 m head available for power generation, the storage reservoir with a pumping facility is highly economical to utilize all the waters of the Kishenganga River flowing in India. Water pumping from the storage works/reservoir could be achieved by installing a pumped storage scheme to generate peaking and secondary power additionally.

Local Concerns

[edit]

Pollution

[edit]

In 2013 local population of Bandipora protested against Hindustan Construction Company (HCC) executing the 330 MW Kishenganga hydroelectric project in the area. The protesters accused the company of causing severe damage to natural environment[47][48] and causing perilous pollution in the area. Following sustained protests by villagers in 2012 and 2013, the hydrology department of National Institute of Technology (NIT) conducted tests in the area and stated pollution had caused chemical disturbance in the water around the project site.The tests revealed high concentration of dissolved solids and unsafe alkaline levels in the water. “The polluted water can neither be used for the human consumption nor for washing purposes,” the report cautioned[47][48]

See also

[edit]

Notes

[edit]
  1. ^ When the Neelum–Jhelum project was completed in August 2018, it was reported that it was reported that it had attained its full generation capacity of 969 MW, and all units of the project were generating power to their maximum capacity.[16]
  2. ^ The chairman of the panel was Judge Stephen Schwebel, former president of the International Court of Justice (ICJ). Frankin Berman and Howard S. Wheater were the legal and engineer members respectively. India nominated Lucius Catflisch and Judge Peter Tomka, president of ICJ. Pakistan nominated Jan Paulsson and Judge Bruno Simma.[18]
  3. ^ The 'dead storage' as defined in the IWT is the water storage in the dam's reservoir above the level of inlets, used for power generation, with adequate submergence to facilitate smooth water inflow. The storage above this level is called 'live storage'. While the live storage fluctuates, the dead storage stays in the reservoir and accumulates sediments that wash down from upstream if not able to pass downstream. The recommended international practice is to flush the dead storage periodically to clear the coarse sediments accumulated in the reservoir.[22]
  4. ^ The Indian Central Water Commission's guidelines state: "These sluices can be used for undertaking a number of hydraulic sediment evacuation techniques viz; drawdown flushing, sluicing, density venting, etc."[34]

References

[edit]
  1. ^ "330 MW Kishanganga Power Project to be commissioned by Nov next". Daily Excelsior. 14 December 2015. Retrieved 13 March 2016. The sanctioned cost of project was Rs 3642.04 crore and revised cost has touched Rs 5783.17 crore
  2. ^ "CERC interim order Kishanganga HEP tariff (see last page)" (PDF). Retrieved 1 October 2019.
  3. ^ a b c Omair Ahmad (15 June 2018). "The Indus Waters Treaty: caught between a dispute and a hard place". The Third Pole. Retrieved 20 June 2018.
  4. ^ Kishanganga project: Victory claims cloud final arbitration award, The Express Tribune, 22 December 2013.
  5. ^ "NHPC's Kishanganga project fully commissioned". Retrieved 2 April 2018.
  6. ^ "Narendra Modi inaugurates Kishanganga hydropower project in Kashmir". 19 May 2018.
  7. ^ Briscoe 2010, p. 29.
  8. ^ "JandK's Kishanganga hydro project: 9 interesting facts - JandK's Kishanganga hydro project". The Economic Times. Retrieved 4 August 2022.
  9. ^ "Kishanganga". NHPC Limited. Retrieved 3 February 2019.
  10. ^ "CoA verdict dated 18 February 2013 on Kishanganga hydro power project (page 94)". Retrieved 1 October 2019.
  11. ^ a b Khan 2013, p. 215.
  12. ^ a b John Briscoe, Winning the battle but losing the war, The Hindu, 22 February 2013.
  13. ^ Kazi, Asif H. "Misusing the Indus Treaty", The News, 1 July 2011.
  14. ^ a b Tanaka 2012, pp. 556–557.
  15. ^ Ramaswamy R. Iyer, Arbitration & Kishenganga project, The Hindu 25 June 2010.
  16. ^ Neelum-Jhelum project attains full generation capacity of 969MW, The Express Tribune, 14 August 2018.
  17. ^ a b B. G. Verghese, Ideology Threatens Indus Treaty, The South Asian Journal, 25 March 2010.
  18. ^ a b c d Crook 2014, p. 309.
  19. ^ a b c Crook 2014, p. 310.
  20. ^ a b c Crook 2014, p. 311.
  21. ^ a b Crook 2014, p. 312.
  22. ^ A. Schleiss & G. de Cesare, Baglihar Hydroelectric Plant - Assessment of reservoir sedimentation and its effects on the power intake, the pondage, and the upstream flood safety, Baglihar Expert Determination, Annex 6.3, 22 December 2006, paragraph 1.2.
  23. ^ Akhter 2013, p. 25.
  24. ^ Akhter 2013, p. 25: "The height of sluice spillways was contested because this seemingly mundane design feature has stark geopolitical implications for upstream/downstream dynamics. While sluice spillways improve the economic life of the dam by enabling flushing of silt, they also give the upstream riparian greater capacity to control the flow of water."
  25. ^ Crook 2014, p. 311: "Pakistan saw such flushing as threatening its right to stable and uninterrupted flows, since flows could surge during reservoir flushing and shrink, or even disappear, during refilling."
  26. ^ B. G. Verghese, Ideology Threatens Indus Treaty, The South Asian Journal, 25 March 2010. Quote: "Zulfiqar Ali Bhutto held up the run-of-the-river Sallal project in the 1980s on the ground that this could be used strategically against Pakistan as an instrument of war, to pond and dry up the river, or suddenly release ponded waters to flood Pakistan in time of war and bog down its armour."
  27. ^ a b c Feisal Naqvi, The Kishenganga Conundrum, Dawn, 18 November 2018
  28. ^ Reports 2018, Partial Award, paragraph 311, p. 168.
  29. ^ Crook 2014, pp. 311–312.
  30. ^ John Briscoe, Peace, not war, on the Indus, The Hindu, 31 December 2013.
  31. ^ a b "Partial Award dated 18 February 2013 on Kishenganga project". Retrieved 22 September 2022.
  32. ^ "Wishing away water woes". Retrieved 7 April 2023.
  33. ^ Reports 2018, Partial Award, paragraph 287, p. 160.
  34. ^ Guidelines for Sediment Management in Water Resources & Hydropower Projects, Central Water Commission, Government of India, February 2019.
  35. ^ Reports 2018, Partial Award, paragraph 140, pp. 111–112.
  36. ^ Reports 2018, Partial Awards, paragraph 144, p. 112.
  37. ^ a b Pak to approach World Bank over water dispute with India, The Economic Times, 28 September 2009.
  38. ^ Breaking excavation records in the Himalayas, TunnelTalk, December 2012.
  39. ^ Nirupama Subramanian, Long objected by Pakistan, Kishanganga Hydro Electric Project set for inauguration next month, The Indian Express, 30 April 2018.
  40. ^ J&K's Kishanganga hydro project: 9 interesting facts, The Economici Times, 2 July 2014.
  41. ^ HCC rallies 5% on completion of first tunnel for Kishanganga project, The Economic Times, 12 June 2014.
  42. ^ New award follows Seli Kishanganga success, TunnelTalk, 20 May 2014.
  43. ^ Gilani, Syed Manzoor (2 November 2018). "GB: water conservation and preservation". Daily Times.
  44. ^ "Lower Jhelum Hydroelectric Project JH01065". India-WRIS wiki. Archived from the original on 9 July 2018.
  45. ^ a b Reports 2018, Final award
  46. ^ "The Indus Waters Treaty 1960 (with annexes)" (PDF). United Nations. Retrieved 30 October 2018.
  47. ^ a b "Hindustan construction Company Blasts Rules & Regulations". The Kashmir Scenario. 27 January 2013. Archived from the original on 13 August 2017.
  48. ^ a b Bandipora, Gurez residents face forced migration threat, Greater Kashmir, 14 March 215.

Bibliography

[edit]
[edit]
  • Partial award, The Permanent Court of Arbitration, 18 February 2013
  • Final Award, The Permanent Court of Arbitration, 20 December 2013